DESCRIPTION: Ratify administrative action taken to award contract with LabMar Ferry LLC. for crowd control training and services at Canal Street Ferry Terminal

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

To ratify the Chief Executive Officer’s action for Crowd Control services with LabMar Ferry LLC in the not to exceed amount of $129,200.00.

end

ISSUE/BACKGROUND:

body

The Board previously approved a contract in the amount $109,200.00 for the period of January 2022 through March 2023 at their December 14, 2021 meeting. Additionally, staff entered a requisition in the amount of $20,000 to cover crowd control training and staffing for November and December of 2021.

In accordance with the State Fire Marshall’s guidelines for crowd control, a person is required to be present when there are more than 50 persons onboard the ferry barge at Canal Street Terminal. Crowd control is only required at the temporary facility because there is no secondary egress. 

end

DISCUSSION:

The ratification is requested in an abundance of caution and to avoid any appearance of a split procurement.

Twenty-Five crew members are being trained by an approved State Fire Marshall online course which the certificate is valid for 2 years. The cost of the additional deck hand required for crowd control is ~$240.00 per day or an average of $7280.00 per month. The projected timeline is November 2021 through March 2023.

FINANCIAL IMPACT:

The project is funded through grant number LA95006.1047.123405 in the amount of $129,200.00.

NEXT STEPS:

UPON RTA Board approval, staff will issue a Notice to Proceed (NTP) on training to LabMar.

ATTACHMENTS:

1.                     Resolution

 

 

 

Prepared By:                                          Darrell LaFrance, lfrance@rtaforward.org

Title:                                                               Project Manager, III

                                          

Reviewed By:                     Lona Edwards Hankins, lhankins@rtaforward.org

Title:                                                               Deputy CEO of Planning, Infrastructure and Information Technology

 

Reviewed By:                     Gizelle Johnson Banks

Title:                                                               Chief Financial Officer

 

 

 