File #: 21-136    Version: 1
Type: Resolution Status: Passed
File created: 8/25/2021 In control: Board of Commissioners
On agenda: 9/28/2021 Final action: 9/28/2021
Title: Canal Street Ferry Terminal Project: Amendment Request to Woodward-APC's Contract
Attachments: 1. Board Resolution, 2. 2021-08-24 CSFT - CCD #005, 3. RTA CSFT COR 025 Approval, 4. Amendment Request to Woodward-APC's Contract
Related files: 22-147, 22-118, 22-065, 22-064, 23-124, 22-117
title
Canal Street Ferry Terminal Project: Amendment Request to Woodward-APC's Contract
end
DESCRIPTION: Requesting Board Authorization to Amend Woodward-APC's Contract Due to Steel Escalation Cost
AGENDA NO: Click or tap here to enter text.

ACTION REQUEST:
? Approval ? Review Comment ? Information Only ? Other

RECOMMENDATION:
recommendation
To authorize the Chief Executive Officer to amend Woodward-APC's contract for a not-to-exceed amount of $250,000 pay for the cost of steel escalation.
end
ISSUE/BACKGROUND:
body
In June of 2021, the Board authorized staff to negotiate a change order for the permanent barge for a not-to-exceed amount of $700,681.16. Staff was able to reduce the amount and process the change order in the amount of $657,443.16. Any consideration of increase of steel cost due to escalation was removed from this change order
end
DISCUSSION:
The contract price for the construction of the permanent barge was established in April of 2020. Staff eliminated the Half Grand Union (HGU) rail connection and utilized the savings to make some design changes that improve operational efficiencies by allowing operations to service larger volumes of passengers quicker, providing operations a secondary method to service ferries utilities, and reduce operation functions by including an internal ballasting system which requires less manpower than the previous system.
While the original plan was to use the HGU savings to support the revised permanent barge cost, the FTA has granted authorization for RTA to use savings from new Ferry Boats purchase. The HGU savings will now be allocated to the project's contingency.
Redesigns were expected to be completed earlier this year but delayed due to slowdowns in regulatory agency permitting. Permitting took longer than expected due to staff availability being reduced by COVID restrictions.
RTA Staff issued a Construction Change Directive (CCD) to mitigate the risk of steel prices further increasing and...

Click here for full text