Attachments: 1. Attachment 1 - Board Resolution Amend Woodward-APCs Contract, 2. Attachment 2 - PCCOR #026 R1, 3. Attachment 3 - Royal Cost Analysis and Recommendation, 4. Attachment 4 - MiNO's Recommendation, 5. Attachment 5 - ICE Form, 6. Attachment 6 - C&C Marine Hull Survey Diminuation, 7. Attachment 7 - Photos, 8. Canal Street Ferry Terminal Project Amendment Request to Woodward APC's Contract.pdf
Related files: 22-147, 22-118, 22-065, 22-064, 23-124, 22-117
title
Canal Street Ferry Terminal Project Amendment Request to Woodward-APC's Contract
end
DESCRIPTION: Requesting Board Authorization to Amend Woodward-APC's contract to include additional repair work to the Jackson Avenue Barge
AGENDA NO: Click or tap here to enter text.

ACTION REQUEST:
? Approval ? Review Comment ? Information Only ? Other

RECOMMENDATION:
recommendation
To authorize the Chief Executive Officer to amend Woodward-APC's contract to include additional Jackson Ave. Barge repair work to the Canal Street Ferry Terminal project.
end
ISSUE/BACKGROUND:
body
In March 2021, C&C Marine, sub-contractor to Woodward-APC, was issued a notice to proceed with modifying the Jackson Ave. Barge into the Canal Street Ferry Terminal (CSFT) project's Temporary Berthing. As part of C&C's scope, C&C completed an Ultrasonic Thickness (UT) test to determine if the barge had sustained any significant losses in thickness. The UTI test yielded that large sections of the hull beneath the waterline had sustained losses of over 25% to 30% of its original thickness.
MiNO, marine engineer subcontracted to Infinity, reviewed the UT test results and stated since these losses were over allowable industry standard thresholds, that it is recommended diminished sections of hull be removed and replaced in order for the barge to be seaworthy.
end
DISCUSSION:
Due to the excessive percentage of hull thickness loss, if repairs are not performed, then the barge would be at an unacceptable level of risk for capsizing and/or sinking due to hull failure. Repairs are required to eliminate all safety risks and bring the barge into a seaworthy state. According to the Marine Engineer MiNO, the barge's seaworthiness applies to both short term use and long- term use, so repairs will be required even for Temporary Berthing use.
According to MiNO and Dupont-LeCorgne, there are two reasons the UT test could not have been performed prior to dry docking. The first was due to hazardous li...

Click here for full text