File #: 20-069    Version: 1
Type: Resolution Status: Passed
File created: 1/18/2021 In control: Board of Commissioners
On agenda: 1/26/2021 Final action:
Title: Canal Street Ferry Terminal Project: Amendment Request to Woodward-APC's Contract
Attachments: 1. Resolution 20-069, 2. Expense Breakdown 20-069
Related files: 22-147, 22-118, 22-065, 22-064, 22-117, 23-124
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Canal Street Ferry Terminal Project: Amendment Request to Woodward-APC's Contract

end

DESCRIPTION: Requesting Board Authorization to Amend Woodward-APC's contract to include repair work to the Jackson Avenue Barge

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

AUTHORIZE the Chief Executive Officer to:

Amend Woodward-APC's contract to included additional Jackson Ave. Barge repair work for the Canal Street Ferry Terminal project.

end

ISSUE/BACKGROUND:

body

In September 2020, at RTA's request, APC Construction completed additional testing to the Jackson Avenue Barge. These tests were to confirm the barge did not sustain damage due to the critical state observed back in May 2020. While APC's Naval Architect concluded that new damage did not occur, existing damage not previously identified was discovered. In order to place the barge safely into revenue service, additional repair work is required.

RTA has requested to add additional improvements to the temporary berthing design in order to improve operability. These include widening the access gangway to allow for faster movement of passengers, demolishing the stair tower, additional utilities, and ballast system repairs. These were previously value engineered out of the project due to budgetary constraints.

This amendment does not include improvements made to the permanent barge. An amendment for changes to the Permanent Barge will be submitted upon completion of the redesign.

end

DISCUSSION:

The plan is to use the Jackson Avenue Barge as the Temporary Berthing during construction of the new Canal Street Ferry Terminal. While testing was completed in 2017, as the barge has remained inactive and adjacent to an active Mississippi River, it has sustained additional wear and tear. APC's Testing results have been provided to Infinity Engineering, who recently completed the repair design.

Added items will reduce operational functions, as well as allow the RTA to maintain shorter headways. While these added items are not needed to put the temporary berthing into revenue service, they will improve overall operational efficiency.

FINANCIAL IMPACT:

The rough order of magnitude to complete the additional repairs is $610,000, and will be funded through Grant LA 2017-019.12.73.00, which has an available balance of $1,130,629. Staff will continue to negotiate this price down as the pricing is finalized. The following is a breakdown of the $610,000 cost:

                                                                                                                                                                                             

Cost of Work Not Previously Identified

 Cost

Cost of Improvements Recommended By Ferry Operations

 Cost

Tow Barge to Repair Site in Morgan City Dry-dock Barge                                                       

$50,000

Demolition of Stair Tower

$91,000

Dry-dock Barge

$24,000

Repairing Ballast System

$129,000

Sand Blasting and Painting Barge

$78,000

Additional Utilities

$50,000

Additional Testing and Surveying

$6,400

 

 

TOTAL

$339,400.00

TOTAL

$270,000.00

 

NEXT STEPS:

Upon Board approval, staff will amend Woodward-APC's contract to include repair work in their contract.

During the performance of this contract, staff will conduct ongoing dialogue to the Board during the project development.

ATTACHMENTS:

1.                     Board Resolution

2.                     Rough Order of Magnitude (ROM) of Jackson Avenue Barge Repair Work

3.                     Potential Change Order Tracking Log

4.                     Contingency and Savings Tracking Log

 

Prepared By:                                          Stephen Mitchell, Infrastructure Project Manager, Infrastructure Department  smitchell@rtaforward.org 

                                                               

 

                                                               

                                                               

Reviewed By:                     Lona Edwards Hankins, Chief of Infrastructure & Planning Infrastructure Department  lhankins@rtaforward.org

                                                               

                                                               

                                                               

 

 

 

 

                                                               Click or tap to enter a date.

Alex Wiggins                                                                                                                                                                        Date

Chief Executive Officer