Attachments: 1. Resolution, 2. CO- Time Impact Analysis of Temporary Berthing-Time Delay, 3. PCCOR 053R5
Related files: 23-124
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

Canal Street Ferry Terminal Project: Amendment Request to Woodward-APC’s Contract

end

DESCRIPTION: Requesting Board Authorization to Amend Woodward-APC’s contract to include the Time Delay Claim

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Ratification of Resolution 22-028 that authorized an amendment to Woodward-APC’s contract for a not-to-exceed original amount of $500,000.00 for the Time Delay Claim, for the final negotiated amount of $585,000.00.

end

ISSUE/BACKGROUND:

body

Shortly after the Notice to Proceed (NTP) was issued the RTA had to issue a notice to Woodward-APC (WAJV) to put the fabrication of the new gangway and modification of the temporary berthing barge on hold.  This hold was in response to operational needs, a community request for a wider gangway, and a detailed condition assessment of the then dry-docked temporary barge. These items required redesign and approval by the various regulatory agencies. 

These items were on the critical path because demolition of the existing terminal could not take place until the temporary berthing location was open. This hold lasted from September 11, 2020, until March 11, 2021, when the design for the last item was completed.  The original delay claim was 205 days for $950,000.00 it was recognized that the initial time impact analysis did not accurately forecast the completion date. The revised delay is 122 days and not to exceed $500,000.00. The Final Delay Claim Agreement was negotiated between RTA, Royal, Dupont-LeCorgne and Woodward/APC for additional general conditions, materials, equipment, and subcontract cost calculated and outlines the methodology for the additional $85,000.00.

end

DISCUSSION:

This change order delay claim request is for additional contract time and cost owed to Woodward/APC due to the owner responsible delays to the critical path of the project.

The original Change Order Request (COR) including 209 days for $950,000.00 was negotiated down based on the following factors.

                     Staff performed a critical review of the WAJC schedule submitted with the COR to more accurately account for the schedule acceleration provided by the RTA to drive piles in advance of the high river.

                     The number of float days in the schedule was reduced by 22.

                     Changed the way the General Conditions were calculated for this change order

 

FINANCIAL IMPACT:

The original total cost for this work was not to exceed $500,000.00 and will be funded through 1FERRY.1047 and other local sources if needed. Staff has continued to negotiate this price as the pricing is finalized. The final negotiated amount of $585,000.00.

NEXT STEPS:

Upon Board approval, staff will amend Woodward-APC’s contract to include the Time Delay Claim

ATTACHMENTS:

1.                     Resolution

 

 

 

Prepared By:                                          Darrell LaFrance, dlafrance@rtaforward.org

Title:                                                               Project Manager III

                     

                                          

Reviewed By:                     Lona Edwards Hankins, lhankins@rtaforward.org

Title:                                                               Deputy Chief of Infrastructure, Planning and Information Technology

 

Reviewed By:                     Gizelle Johnson Banks

Title:                                                               Chief Financial Officer

 

 

                                                               11/7/2022

Alex Wiggins                                                                                                                              Date