File #: 21-062    Version: 1
Type: Resolution Status: Passed
File created: 4/23/2021 In control: Board of Commissioners
On agenda: 5/25/2021 Final action: 5/25/2021
Title: Rampart Streetcar Line: Emergency Recovery Project Award Construction Project
Attachments: 1. 1- Board Resolution - Award Construction Contract, 2. 2. AECOM Opinion of Probable Construction Cost, 3. Rampart Streetcar Line Emergency Recovery Project Award Construction Project.pdf
Related files: 21-100, 22-103
title
Rampart Streetcar Line: Emergency Recovery Project Award Construction Project
end
DESCRIPTION: Requesting Board Authorization to Award a Construction Contract to the Lowest Responsive Bidder
AGENDA NO: Click or tap here to enter text.

ACTION REQUEST:
? Approval ? Review Comment ? Information Only ? Other

RECOMMENDATION:
recommendation
Authorize the Chief Executive Officer to award a construction contract to the lowest responsive bidder to repair sections of the Canal Streetcar Line impacted by the collapse of the Hard Rock Hotel. According to AECOM's opinion of probable cost, the total estimated cost to restore Canal St, excluding the Rampart connector, is $270,000.00.
end
ISSUE/BACKGROUND:
body
As decreed by Mayor LaToya Cantrell in March of 2020, the RTA was directed to restore the infrastructure impacted by the Hard Rock Hotel collapse as quickly as possible. However, as the Hard Rock Hotel Developer (hereby referred to as the "Developer") has obstructed RTA's infrastructure along Canal Street until recently, the RTA is working to restore the Canal Streetcar Line by the end of July.
end
DISCUSSION:
In February 2021, the Developer removed demolition equipment and crane mats along Canal Street, allowing RTA's engineer, AECOM to complete damage assessments of the Canal Streetcar Line. The repair package was completed on April 16th. The RTA is now working to solicit a contractor to complete the repairs. As the City has reopened lake bound Canal Street, the RTA is requesting Board Authorization to award a Construction Contract early to meet the schedule to restore the Canal Streetcar line by the end of July. As the developer is still obstructing the Rampart Streetcar Line, as well as the long lead times for damaged materials, restoration of the Rampart Streetcar Line will be handled as a separate project to be completed later this year.
FINANCIAL IMPACT:
AECOM's Opinion of Construction Cost to restore the Canal Streetcar Line is not expect...

Click here for full text