File #: 22-016    Version: 1
Type: Resolution Status: Passed
File created: 1/21/2022 In control: Board of Commissioners
On agenda: 2/22/2022 Final action: 2/22/2022
Title: Rampart Streetcar Emergency Recovery Project: Amend AECOM's Engineering Contract
Attachments: 1. Proposal Amendment No 2_7-27-21, 2. Rampart Change Order AECOM, 3. R22-011: Rampart Streetcar Emergency Recovery Project
Related files: 22-103

title

Rampart Streetcar Emergency Recovery Project:  Amend AECOM’s Engineering Contract

end

DESCRIPTION: Requesting Board Authorization to Amend AECOM’s for the Rampart Streetcar Recovery Project

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Authorize the Chief Executive Officer to amend AECOM’s contract in the amount of $107,923.26 to provide additional design services for the Rampart Streetcar Emergency Recovery at the Hardrock Site. The total contract cost will be $234,603.05.

 

end

ISSUE/BACKGROUND:

body

The Base Contract was for the assessment of the Rampart Streetcar Line as the result of the Hard Rock collapse (but did not include design) is for $63,889.70.

 

Amendment 1 added the design of the repairs for the Rampart Streetcar and Canal Streetcar lines modification from Rampart to Loyola/Elk Place.  Additionally, they were tasked with assessing the grout and traction power boxes (but did not include a design), an increase of $126,679.79.

 

end

DISCUSSION:

Amendment 2 is for design required to replace the elastomeric grout at Canal/Rampart intersection and the repair required for the traction power boxes, at a cost $107,923.26.

FINANCIAL IMPACT:

AECOM’s total not-to-exceed fee for the amended services will be $234,603.05 and will be funded through local account 1.1510.109.

NEXT STEPS:

Upon Board approval, staff will award a Design/Engineer contract to AECOM.

ATTACHMENTS:

1.                     Resolution

2.                     Vendor Proposal-Amendment 2

3.                     Change Order Request

 

 

 

 

Prepared By:                                          Darrell LaFrance, dlfrancel@rtaforward.org

Title:                                                               Project Manager, III

                     

                                          

Reviewed By:                     Lona Edwards-Hankins, lhankins@rtaforward.org

Title:                                                               Deputy CEO of Planning, Infrastructure, and Information Technology

 

Reviewed By:                     Gizelle Johnson Banks

Title:                                                               Chief Financial Officer

 

 

                                                               2/8/2022

Alex Wiggins                                                                                                                              Date

Chief Executive Officer