File #: 24-089    Version: 1
Type: Resolution Status: Agenda Ready
File created: 8/23/2024 In control: Board of Commissioners
On agenda: 11/26/2024 Final action:
Title: FY2021 Low-No Emissions Bus Program
Attachments: 1. Resolution_8-23-2024, 2. New Orleans RTA - New Flyer Revised XE40 Proposal, 3. BID 22-316-IS NORTA Charger Scope Proposal 6-20-24, 4. New Orleans RTA - New Flyer Final Proposal (003), 5. Board Resolution 23-025, 6. Grant Award - LA-2024-031-00 - Sept 2024
Related files: 21-036, 23-041
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

FY2021 Low-No Emissions Bus Program

end

DESCRIPTION: Reauthorize execution of a contract with Low-No Emissions bus vendor for buses and associated charging infrastructure at a revised contract price

AGENDA NO: Click or tap here to enter text. 

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Reauthorize the Chief Executive Officer to execute a contract with New Flyer of America for the purchase of three low-no emissions buses and construction of associated charging infrastructure for an amount not to exceed $6.4M.

end

ISSUE/BACKGROUND:

body

The FY2021 Low-No Emissions Grant was approved in the summer of 2021 and coauthored by New Flyer, the bus manufacturer, as allowed by FTA for this grant program.  The federal grant amount is $5.15M and was awarded in September, 2024. The Performance End Date of the grant is March 30, 2026.  The contract pricing previously authorized by the Board (Resolution No. 23-025 on April 25th, 2023) was for $5.7M for three (3) 40’ electric buses and the necessary charging infrastructure. No contract has been executed to date.

The June 2024 revised pricing, which is for the same number of buses and associated infrastructure, increased the overall cost by $620K. Staff is budgeting an additional $1.0M for this project to cover this $620K cost increase and $380K for project contingency (6% of the overall project cost).

end

DISCUSSION:

Pricing with the vendor cannot be locked in until a purchase order is issued. The FTA released the grant funds associated with the No Emissions Bus Pilot (Low-No 2021) in September, 2024. Furthermore, the transition in the RTA’s financial system impacted staff’s ability to set up new capital projects and associated purchase orders. Delays in the release of funds contributed to increased costs due to supply chain and inflation related issues.

As issuance of a purchase order will lock in pricing, staff does not anticipate any cost overruns, though a project contingency has been included in the budget in the unlikely event of any complications.

FINANCIAL IMPACT:

This authorization will allow the project team to execute a contract with our partner, New Flyer, on the design and procurement of buses and infrastructure, thereby minimizing impact to the project schedule while also locking in current pricing.

The increase in budget-both for the revised contract amount and for project contingency-translates to approximately $750K in additional local match. This increment will be sourced from RTA’s adopted 2024 capital budget and the account number is 01-0000-00-1501-000-00-00-00000-00000.

 

NEXT STEPS:

Upon Board approval to move forward with this contract execution, the project team will issue a purchase order and notice to proceed with New Flyer and will initiate the procurement of the three (3) 40’ electric buses and associated charging infrastructure. Staff expects the manufacture and delivery of the buses to take 18-24 months based on the current backlog of orders, although the RTA’s position in the queue could improve depending on the manufacturer’s capacity and status of other orders.

ATTACHMENTS:

1.                     Resolution

2.                     Revised pricing proposal from New Flyer dated June 13, 2024 for vehicles and charging rails

3.                     Revised pricing proposal from New Flyer date June 24, 2024 for charging infrastructure

4.                     Pricing proposal from New Flyer dated January 31, 2023

5.                     Board Resolution 23-025

6.                     Grant agreement for LA2024-03

 

 

Prepared By:                                          Rafe Rabalais, rrabailais@rtaforward.org

Title:                                                               Director of Capital Projects

                     

Reviewed By:                     Dwight Norton, dnorton@rtaforward.org

Title:                                                               Chief of Infrastructure and Planning

 

Reviewed By:                     Gizelle Johnson-Banks

Title:                                                               Chief Financial Officer

 

                                                               10/14/2024

Lona Edwards Hankins                                                                                                                              Date

Chief Executive Officer