File #: 21-100    Version: 1
Type: Resolution Status: Passed
File created: 6/24/2021 In control: Board of Commissioners
On agenda: 7/27/2021 Final action: 7/27/2021
Title: Rampart Streetcar Line Emergency Recovery Project Award Construction Project
Attachments: 1. 1. Board Resolution, 2. 2. May Board Approval, 3. 3. Walter J Barnes Electric Bid, 4. 4. Administrative Review Form IFB 2021-009, 5. 5. Procurement Summary - IFB 2021-009 Rampart Emergency Repair, 6. Rampart Streetcar Line Emergency Recovery Project Award Construction Project .pdf
Related files: 21-062, 22-103

title

Rampart Streetcar Line Emergency Recovery Project Award Construction Project

end

DESCRIPTION: Requesting Board Authorization to Ratify Award of Construction Contract to Walter J. Barnes Electric Company, Inc.

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Ratify a construction contract awarded to Barnes Electric by the Chief Executive Officer to repair sections of the Canal Streetcar Line impacted by the collapse of the Hard Rock Hotel.

end

ISSUE/BACKGROUND:

body

As the lowest responsive bid is over the Board Approved not-to-exceed cost of $270,000.00, RTA staff is requesting Board authorization to ratify award of the construction contract to Barnes Electric for $289,000.00.

 

end

DISCUSSION:

RTA Staff previously presented a Board agenda item at the May Board to award a contract to repair sections of the Canal Streetcar Line impacted by the Hard Rock Hotel Collapse. As cost are greater than the approved amount, staff is requesting the Board ratify to award the contract to Barnes Electric.

RTA Staff requested Board authorization at the May meeting in order to complete repairs quickly and comply with the Mayor of New Orleans’s Emergency Repair Decree.

 

FINANCIAL IMPACT:

Barnes Electric’s cost to complete this work $289,000.00, which will be funded through local account 1.1510.109. All cost associated with this work will be tracked for financial recovery purposes.

 

NEXT STEPS:

Upon Board approval, staff will continue to manage the construction contract with Barnes Electric to repair the Canal Streetcar Line between South Liberty St. to Baronne St.

 

 During the performance of this contract, staff will conduct ongoing dialogue to the Board during the project development.

 

ATTACHMENTS:

1.                     Board Resolution

2.                     May Board Approval

3.                     Walter J. Barnes Electric’s Bid

4.                     Administrative Review Form - IFB 2021-009

5.                     Procurement Summary - IFB 2021-009

 

 

Prepared By:                                          Dwight Norton, dhorton@rtaforward.org

Title:                                                               Sr. Director of Strategic Planning

                     

                                          

Reviewed By:                     Lona Edwards Hankins, lhankins@rtaforward.org

Title:                                                               Chief of Infrastructure & Planning

 

Reviewed By:                     Gizelle Johnson Banks

Title:                                                               Chief Financial Officer

 

 

 

 

 

                                                               7/2/2021

Alex Wiggins                                                                                                                              Date

Chief Executive Officer