Title: Universal Accessibility Study
Attachments: 1. WSP - RFP 2023-024 Proposal, 2. RFP 2023-024 Universal Study, 3. Universal Accessibility RFP Scope_FINAL, 4. Solicitation Request Routing Sheet_Approved - Univeral Accessibility Study, 5. Procurement Summary - RFP 2023-024, 6. Administrative Review Form RFP 2023-024, 7. Universal Accessibility Study
Related files: 22-139, 23-220

title

Universal Accessibility Study

end

DESCRIPTION: To award the contract to WSP for the Universal Accessibility Study

AGENDA NO: Click or tap here to enter text. 

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Authorize the Chief Executive Officer to execute a contract with WSP to complete a Universal Accessibility Study for the RTA for an amount not to exceed $260,000.

end

ISSUE/BACKGROUND:

body

The RTA’s Strategic Mobility Plan (SMP) includes action BE3: “Complete a comprehensive accessibility study to ensure that all agency activities and RTA service (bus, streetcar, ferry, stops, facilities, technology, information, communication, wheelchair safety) to reflect best practice for access and ADA”. 

RFP 2023-024 for a Universal Accessibility Study was issued in November 2023 to complete this action so that the agency may understand how to update RTA’s services and infrastructure to reflect best practices in accessibility. WSP submitted the successful proposal, which was selected by the evaluation committee to complete this study.

end

DISCUSSION:

WSP will complete the study under the direction of the Planning & Scheduling Department and will accomplish the following deliverables:

 

Task 1 Deliverables

                     Community Outreach and Data Collection Plan detailing the proposed activities and needs for review by NORTA for finalization

                     Technical Memo on best practices for universal accessibility in transit

                     Database of all relevant RTA data collected to develop an accessibility framework for the RTA in editable and easy to manipulate format (e.g. MS Excel)

Task 2 Deliverables

                     Set meeting times, manage meeting logistics and provide agendas for Advisory Committee meetings

                     Prepare presentation materials for Advisory Committee meetings

                     Incorporate feedback from the Advisory Committee into the study

                     Develop a Committee Charter defining participants, role, format and framework for continue to advise NORTA as it works to implement recommendations in Task 6

 

Task 3 Deliverables

                     Universal Accessibility Framework document that describes the RTA’s framework for universal accessibility to guide decision-making in a format that is concise and easy to use. This framework should include the prioritization mechanism to help the RTA prioritize actions related to accessibility improvements

Task 4 Deliverables

                     Baseline Conditions Assessment report, detailing the existing accessibility landscape at the RTA including the elements listed above.

Task 5 Deliverables

                     Gap Analysis Technical Memo, describing the accessibility gaps identified.

                     Updated Universal Accessibility Framework, as needed

Task 6 Deliverables

                     Recommendations report, describing recommended actions, estimated resources needed for the actions, and suggested timeline for completing the recommendation.

The above tasks and deliverables are estimated to be completed in 12 months from notice-to-proceed (NTP).

FINANCIAL IMPACT:

This study will be funded through RTA local funds. The budget code is 01-2800-02-7070-173-00-00-00000-00000-00.

NEXT STEPS:

Procurement to issue the contract to WSP and Planning to kick off the project.

ATTACHMENTS:

1.                     Resolution

2.                     WSP Proposal

3.                     RFP 2023-024 Universal Study

4.                     Universal Accessibility RFP Scope

5.                     Solicitation Request Routing Sheet

6.                     Procurement Summary

7.                     Administrative Review Form

 

 

 

 

 

 

 

 

Prepared By:                                          Joanna Farley, jfarley@rtaforward.org

Title:                                                               Senior Transportation Planner

                     

                                          

Reviewed By:                     Dwight Norton, dnorton@rtaforward.org

Title:                                                               Chief of Infrastructure, Planning, and Information Technology

 

Reviewed By:                     Gizelle Johnson-Banks

Title:                                                               Chief financial Officer

 

                                                               6/3/2024

Lona Edwards Hankins                                                                                                                              Date

Chief Executive Officer