Skip to main content
File #: 20-071    Version: 1
Type: Resolution Status: Passed
File created: 1/18/2021 In control: Board of Commissioners
On agenda: 1/26/2021 Final action: 1/26/2021
Title: St. Charles Streetcar Line: ADA Project: Cooperative Endeavor Agreement between City of New Orleans and RT A
Attachments: 1. 20-071-Resolution-CEA between RTA and CNO-St Charles Streetcar Line ADA Project, 2. 20-071-Cost Information-CEA between RTA and CNO-St Charles Streetcar ADA Project
Related files: 25-085
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

title

St. Charles Streetcar Line: ADA Project: Cooperative Endeavor Agreement between City of New Orleans and RT A

end

DESCRIPTION: Requesting Board Authorization to Negotiate and Approve a Cooperative Endeavor Agreement with the City of New Orleans

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

AUTHORIZE the Chief Executive Officer to:

Negotiate and Approve a Cooperative Endeavor Agreement (CEA) between the City of New Orleans and RTA.

end

ISSUE/BACKGROUND:

body

The St. Charles Streetcar Line: ADA Accessibility Project has been completed. During the project life cycle, RTA managed and funded engineering, while the City of New Orleans (CNO) managed and funded construction. As there is a letter agreement between RTA and CNO to equally share project costs, a Cooperative Endeavor Agreement (CEA) is needed to reimburse CNO as construction costs exceed engineering costs.

end

DISCUSSION:

The Total Project cost is $561,898.35. Since RTA only paid $157,134.45 for engineering, while the CNO paid $404,763.90 for construction, RTA must reimburse CNO $123,814.73 to offset costs.

FINANCIAL IMPACT:

RTA will reimburse the CNO $123,814.73 and will funded this cost through local account 1.1122

NEXT STEPS:

Upon Board approval, staff will negotiate and approve a cooperative endeavor agreement with the City of New Orleans

ATTACHMENTS:

1.                     Board Resolution

2.                     Letter Agreement dated April 17th, 2017

3.                     CEA Cost Breakdown Summary

 

Prepared By:                                          Stephen Mitchell, Infrastructure Mitchell, Department Infrastructure Project Manager, smitchell@rtaforward.org

                                                               

 

                                                               

                                                               

Reviewed By:                     Lona Infrastructure Edwards Hankins, Department Chief of Infrastructure & Planning, lhankins@rtaforward.org

                                                               

                                                               

                                                               

Reviewed By:                     Gizelle Banks, Chief Financial Officer Finance Department, Gbanks@rtaforward.org

                                                               

                                                               

 

 

 

 

                                                               Click or tap to enter a date.

Alex Wiggins                                                                                                                                                                        Date

Chief Executive Officer