File #: 21-038    Version: 1
Type: Resolution Status: Passed
File created: 3/29/2021 In control: Board of Commissioners
On agenda: 6/22/2021 Final action: 6/22/2021
Title: Connecting Communities-NORTA Bus Rapid Transit (BRT) Planning Project
Attachments: 1. 2021.04.08 Board Resolution - HOPE, 2. ILSI BRT Proposal 022621, 3. 210222_RTA_BRTFeasibilityStudy_Scope_FINAL
Related files: 22-177, 24-056

title

Connecting Communities-NORTA Bus Rapid Transit (BRT) Planning Project                                                                       

end

DESCRIPTION: Requesting Board authorization to approve the contract with Integrated Logistical Support, Inc. (ILSI) to study BRT Routes

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Authorize the Chief Executive Officer to approve a contract with Integrated Logistical Support, Inc. (ILSI), an 8(a) Certified Woman Owned-Minority Owned Small Business, to study Bus Rapid Transit (BRT) routes in the amount of $599,949.00.

end

ISSUE/BACKGROUND:

body

The RTA was awarded a grant as part of the FTA Helping Obtain Prosperity for Everyone (HOPE) Program in FY2020.  The RTA project, Connecting Communities - New Orleans RTA BRT Planning Project will develop design standards to define BRT for the New Orleans region and BRT corridors. The BRT corridors will deliver premium transit to areas of persistent poverty to connect residents to jobs and services. This is aligned with the Agency’s Strategic Mobility Plan-Connect to Opportunities goal. 

end

DISCUSSION:

The Connecting Communities-New Orleans RTA BRT Planning Project will deliver the following:

1)BRT Standards: service planning, guideway design, station amenities and implementation strategy

2)BRT Corridor Plan: project definition and 15% design plans to include ridership projections, traffic analysis, service planning, capital cost estimates and operating and maintenance (O&M) cost estimates.

3) Funding Analysis and Assessment: identify and review funding sources for BRT capital cost including local, state, and federal financing options and potential private sources.

4) Public Engagement: assist the Agency in educating community stakeholders on BRT, gathering input and advice from the community.

5) Project Management:

The contract with ILSI to provide the project deliverables will be managed by the Strategic Planning Department.

FINANCIAL IMPACT:

The portfolio projects is funded from HOPE grant, the total project amount is $611,000, the federal share is $550,000 and the local share is $61,000.

NEXT STEPS:

Procurement to issue the contract to ILSI and Strategic Planning kick off project.

ATTACHMENTS:

1.                     ILSI BRT Proposal 022621

2.                     210222_RTA_BRFTFeasibilityStudy_Scope

3.                     Resolution

 

 

Prepared By:                                          Lona Edwards Hankins, lhankins@rtaforward.org

Title:                                                               Deputy CEO Planning and Infrastructure

                     

                                          

Reviewed By:                     Lona Edwards, lhankins@rtaforward.org

Title:                                                               Deputy CEO Planning and Infrastructure

 

Reviewed By:                     Gizelle Johnson-Banks

Title:                                                               Chief Financial Officer

 

 

 

 

 

                                                               4/6/2021

Alex Wiggins                                                                                                                              Date

Chief Executive Officer