DESCRIPTION: To Authorize the ratification of a three-year contract to Ron Turley Fleet Management System. 

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Authorize the Chief Executive Officer to authorize the ratification of a three-year contract to Ron Turley Fleet Management System (RTA FMS) for the continued use of fleet management software in amount not-to-exceed $194,142.79.

end

ISSUE/BACKGROUND:

body

When TransDev managed the Regional Transit Authority (RTA), one of the software systems brought on board by RTA FMS was the Software as a Service (SaaS) fleet management system from which TransDev managed inventory and maintenance work orders.  First implemented in August 2009, annual renewals were procured via Sole Source (less than $25,000.00) and continued until May 2024 at which time a three-year agreement was reached.

RTA seeks to correct an existing situation. When the RTA took over the annual service payments in 2020, there was no signed contract; instead, there were two separate subscriptions for software and one for maintenance until 2024. When the subscriptions were up for renewal last year, staff managed to work out a three-year deal that locked in the current rate for the first year of the contract and consolidated subscriptions into a single contract. The Asset Management Division seeks a replacement solution and intends to use the two-year span to identify and implement the new solution. 

end

DISCUSSION:

In June 2023, RTA added facilities inventory to move to a unified inventory management system. In 2024, RTA embarked upon a multi-year agreement combining both maintenance and facilities into one, a coterminal agreement to lock in renewal rates and minimize tracking and procurement of two separate renewals. A three-year agreement drafted and signed in May 2024 sought and acquired a PO for the first year of the agreement. The total cost of the three-year agreement, If approved, is not to exceed 194,142.79. The three-year contract will be ratified, and the remaining two years of the contract will be funded. The remaining two-year total is $140,197.79 (roughly $70K annually).

Facilities- Gold Tier

- 5/1/2024 to 4/30/2025: $19,838.00 PO RTAP_00468 issued 5/7/2024

- 5/1/2025 to 4/30/2026: $24,250.45

- 5/1/2026 to 4/30/2027: $28,993.66

 

 

 

 

 

Maintenance- Platinum Tier

- 5/1/2024 to 4/30/2025: $34,107.00 PO RTAP_00412 issued 4/16/2024

- 5/1/2025 to 4/30/2026: $38,435.20

- 5/1/2026 to 4/30/2027: $48,518.48

 

RTA seeks to correct the existing situation and puts forth a resolution that will address and fund the remaining term of the contract. Pending Board approval, the three-year contract year one is ratified for a total cost not to exceed $194,142.79.

The Asset Management Division seeks a replacement solution and intends to use the two-year span to identify and implement the new solution. 

FINANCIAL IMPACT:

The subscriptions will be funded from the IT Departments approved annual operating budget codes 01.2900.02.7140.170.00.00.00000.00000 for a total cost of $194,142.79.

NEXT STEPS:

With Board approval, staff will assign a purchase order and complete the project.

ATTACHMENTS:

1.                     Resolution

2.                     Procurement summary / Routing sheet

3.                     Ron T SaaS 23 Fac PO 915086

4.                     Ron T SaaS 23 Inv PO 914715

5.                     RT-Facilities-PO_RTAP_00468_0

6.                     RT-Maint-PO_RTAP_00412_0

7.                     NORTA Signed Agreement

 

Prepared By:                                          Doris O’Sullivan

Title:                                                               Senior Project Manager of Information Technology

 

Reviewed By:                     Sterlin Stevens

Title:                                                               Director of Information Technology

 

Reviewed By:                     Dwight Norton

Title:                                                               Chief Planning & Capital Projects Officer

 

Reviewed By:                     Gizelle Johnson-Banks

Title:                                                               Chief Financial Officer

 

 

 

                                                               4/1/2025

Lona Hankins                                                                                                                                                                        Date

Chief Executive Officer