File #: 22-010    Version: 1
Type: Resolution Status: Passed
File created: 1/18/2022 In control: Board of Commissioners
On agenda: 2/22/2022 Final action: 2/22/2022
Title: Napoleon Avenue Facility Renovation and Rebuild-403 Napoleon Avenue DESCRIPTION: Stabilization of building to prevent further damage and degradation AGENDA NO: Click or tap here to enter text. ACTION REQUEST: ? Approval ? Review Comment ? Information Only ? Other RECOMMENDATION:
Attachments: 1. 2021 12-16 CDW Bid, 2. 2021 09-21 Analysis of Engineer's Probable Cost Estimate, 3. R22-008: Napoleon Facility Renovation - Correct Version
Related files: 23-181, 23-182, 23-183

title

Napoleon Avenue Facility Renovation and Rebuild-403 Napoleon Avenue

DESCRIPTION: Stabilization of building to prevent further damage and degradation

AGENDA NO: Click or tap here to enter text.

ACTION REQUEST: Approval     Review Comment  Information Only    Other

 

RECOMMENDATION:

recommendation

Authorize the Chief Executive Officer to award a contract to CDW Services, LLC in the amount of $4,742,000.00 for the Scope of Work designated as Base Bid and Alternate 1 items in the Louisiana Uniform Public Bid Form.

end

ISSUE/BACKGROUND:

body

The Napoleon Avenue Facility is a historic building that was built in 1892 as a power station for the historic St. Charles Streetcar Line.  It was later used as a training and storage facility. In 2005 the building was severely damaged during Hurricane Katrina, which triggered the need to plan for repairs and renovation of the facility. This project is to bring the building to a warm, safe dry status, limited to structural, mechanical, and electrical services to prevent further damage and degradation.  This project has been closely coordinated with FTA, SHPO and FEMA.

 

end

DISCUSSION:

An engineering package which details the scope of work has been completed by Landmark Consulting. The drawings and specifications were the documents provided to potential bidders by way of the RTA ProcureWare System. The funding available will be sufficient for items designated as base bid and alternate 1 as per the Engineering Package.

FINANCIAL IMPACT:

The construction funding is being made available by the following sources:

LA04-0038 in the amount of $2,121,152.00, FEMA PW #4159 in the amount of $686,117.00 and 2022 fiscal year local budget in the amount of $1,934,731.00.  Total from all three sources is $4,742,000.00.

NEXT STEPS:

Upon RTA Board approval, an award letter will be issued to CDW Services, LLC and a purchase order will be requested.

ATTACHMENTS:

1.                     Resolution

2.                     CDW Services, LLC Base Bid Description of Work

3.                     Landmark Consulting Estimate of Probable Cost

 

 

Prepared By:                                          Rose Quezergue, rquezergue@rtaforward.org

Title:                                                               Project Manager II

                     

                                          

Reviewed By:                     Lona Edwards-Hankins, lhankins@rtaforward.org

Title:                                                               Deputy CEO of Planning, Infrastructure and Information Technology

 

Reviewed By:                     Gizelle Johnson Banks

Title:                                                               Chief Financial Officer

 

 

                                                               2/2/2022

Alex Wiggins                                                                                                                              Date

Chief Executive Officer